What's the gist?
With New York City facing summer heat waves and grid strain, Councilmember James Gennaro has introduced legislation to make battery storage easier to install. The move puts him in direct conflict with Con Edison, which critics say is making it too expensive for developers to connect battery systems to the grid.
Context
New York State has a goal of 6,000 megawatts of energy storage by 2030, but progress has slowed sharply — only 16.3 megawatts were installed this year, down from 57.6 in 2025. Con Ed's newer interconnection policies are widely blamed for the slowdown, drawing pushback from developers, advocates, and now city lawmakers.